Windmill Ridge Road Bridge Deck Replacement

This project was completed the week of November 6, 2017. 

This project totaled $65,000 and included:

  • The removal and replacing of the existing bridge deck

Construction Dates: 
November 6-10, 2017

Approved Budget: 
$65,000

Design By: 
Volkert

Contractor: 
Pope Contracting