Waterway East Boulevard Extension and Connector Construction Update

Latest News Posted on February 24, 2026

The City of Gulf Shores is preparing to begin Phase 2 of the Waterway East project, thanks to a RESTORE grant that covers all construction costs.

๐—ฃ๐—ต๐—ฎ๐˜€๐—ฒ ๐Ÿญ: Extend the section from 2nd Street to the edge of ALDOTโ€™s right-of-way for the new SR-161 road and bridge.

๐—ฃ๐—ต๐—ฎ๐˜€๐—ฒ ๐Ÿฎ (Coming Soon): Extend Waterway East to connect with SR-161 north of the new bridge.

๐—ช๐—ต๐—ฎ๐˜โ€™๐˜€ ๐—ก๐—ฒ๐˜…๐˜?

โ€ข Waiting on DCNR to issue a Notice to Proceed

โ€ข Construction anticipated to begin in March and finish by the end of summer

โ€ข Project must be completed before the grant deadline in September

โ€ข The grant reimburses Gulf Shores for all eligible costs

This extension will improve traffic flow and connectivity for residents and visitors. Visit us on social media for updates!

DJI_20260223140642_0035_D

DJI_20260223141548_0061_D

๐— ๐—ฎ๐—ฝ ๐—ข๐˜ƒ๐—ฒ๐—ฟ๐˜ƒ๐—ถ๐—ฒ๐˜„:

โ€ข Yellow = ALDOT SR-161 road & bridge

โ€ข Blue = Phase 1 of Waterway East

โ€ข Red = Phase 2 of Waterway EastWaterway EAST Connector Map


  1. Gulf Shores Alabama

Contact Us

  1. City of Gulf Shores

  2. 1905 W 1st Street

  3. P.O. Box 299

  4. Gulf Shores, AL 36547

  5. Phone:  251-968-2425

Helpful Numbers

  1. Emergency :  Dial 911

  2. City Hall :  251-968-2425

  3. Utilities:  251-968-6323

  4. Baldwin EMC:  800-837-3374

  1. Small Town Big Beach

Government Websites by CivicPlus®
Arrow Left Arrow Right
Slideshow Left Arrow Slideshow Right Arrow