[ARCHIVED] Waterway Village Pedestrian Bridge Progress Update

Pedestrian Bridge Construction 1

Crews are moving right along on the Waterway Village Pedestrian Bridge. As of Friday, we've reached 53.6% of our original contract time, with construction making steady progress across all sectors. Here is the latest from the site:

๐‘๐จ๐š๐๐ฐ๐š๐ฒ ๐–๐จ๐ซ๐ค

Concrete and Roadway teams are finishing up work on ALT 1 this week. This includes the final touches like remaining sod, parking bumpers, and permanent signage. Meanwhile, construction on curbs, sidewalks, and entrances is continuing on the east side of ALT 2.

๐๐ซ๐ข๐๐ ๐ž ๐‚๐จ๐ง๐ฌ๐ญ๐ซ๐ฎ๐œ๐ญ๐ข๐จ๐ง

Itโ€™s a big week for the bridge structure. The contractor is scheduled to pour the 3rd vertical section of the South bridge columns this Friday. On the north side, the Bridge Pile cap is currently curing, and crews have begun erecting the rebar for the columns.

๐„๐ฅ๐ž๐ฏ๐š๐ญ๐จ๐ซ ๐“๐จ๐ฐ๐ž๐ซ๐ฌ

Procurement and submittals are ongoing. The North Elevator Tower Pile Cap is curing, and we expect to start vertical wall concrete construction by the middle of next week. Work also continues on the internal slabs and components of the South Elevator Tower.

๐“๐ซ๐š๐Ÿ๐Ÿ๐ข๐œ ๐”๐ฉ๐๐š๐ญ๐ž๐ฌ

โ€ข ALT 1 was opened to normal traffic operations on Sunday, March 1st.

โ€ข Access for work north of the ICW remains open to local traffic only during the ALT 2 construction phase.

๐“๐ฐ๐จ-๐–๐ž๐ž๐ค ๐‹๐จ๐จ๐ค ๐€๐ก๐ž๐š๐

โ€ข Roadway: Construction of ALT 2 entrances, curbs, and sidewalks will continue through the end of March.

โ€ข Bridge & Towers: Work continues on the South Elevator Tower and South Bridge columns.

โ€ข Coming Soon: Construction of the North Bridge Columns and North Elevator Tower Walls is scheduled to begin in mid-March.

The anticipated completion date remains January 8, 2027.

๐“๐ก๐š๐ง๐ค ๐ฒ๐จ๐ฎ ๐Ÿ๐จ๐ซ ๐ฒ๐จ๐ฎ๐ซ ๐ฉ๐š๐ญ๐ข๐ž๐ง๐œ๐ž ๐š๐ฌ ๐ฐ๐ž ๐œ๐จ๐ง๐ญ๐ข๐ง๐ฎ๐ž ๐ฐ๐จ๐ซ๐ค๐ข๐ง๐  ๐ญ๐จ ๐ฆ๐š๐ค๐ž ๐†๐ฎ๐ฅ๐Ÿ ๐’๐ก๐จ๐ซ๐ž๐ฌ ๐š ๐ฌ๐š๐Ÿ๐ž๐ซ, ๐ฆ๐จ๐ซ๐ž ๐ฐ๐š๐ฅ๐ค๐š๐›๐ฅ๐ž ๐œ๐จ๐ฆ๐ฆ๐ฎ๐ง๐ข๐ญ๐ฒ.๐Ÿ‘

Pedestrian Bridge Construction 1

Pedestrian Bridge Construction 2

Pedestrian Bridge Construction 3

Pedestrian Bridge Construction 4

Facebook Twitter Email

Other News in Latest News

Spring Market 2025

Spring Market 2026 Coming Soon!

Posted on: March 11, 2026
West Beach Blvd

TAP Grant Bringing Pedestrian Safety Improvements to W Beach Blvd!

Posted on: March 9, 2026 | Last Modified on: March 9, 2026
Gulf Shores Special Olympian Leighann Landrum

Cheering on Our Special Olympians!

Posted on: March 3, 2026
Arbor Day

Gulf Shores Community Unites to Celebrate Arbor Day!

Posted on: February 24, 2026 | Last Modified on: March 11, 2026
GCAA Tile

2025 Nonprofit Grant Recipient Spotlight: Gulf Coast Arts Alliance

Posted on: February 3, 2026 | Last Modified on: February 3, 2026
Copy of Special Recycling Days

Special Recycling Drive

Posted on: March 21, 2026
GSPD Blessing

Justice Center Blessing

Posted on: January 13, 2026
GSFR First Aid Courses

Gulf Shores Fire Rescue Offering Essential First Aid & CPR Courses

Posted on: January 9, 2026 | Last Modified on: January 23, 2026