Crews are moving right along on the Waterway Village Pedestrian Bridge. As of Friday, we've reached 53.6% of our original contract time, with construction making steady progress across all sectors. Here is the latest from the site:
๐๐จ๐๐๐ฐ๐๐ฒ ๐๐จ๐ซ๐ค
Concrete and Roadway teams are finishing up work on ALT 1 this week. This includes the final touches like remaining sod, parking bumpers, and permanent signage. Meanwhile, construction on curbs, sidewalks, and entrances is continuing on the east side of ALT 2.
๐๐ซ๐ข๐๐ ๐ ๐๐จ๐ง๐ฌ๐ญ๐ซ๐ฎ๐๐ญ๐ข๐จ๐ง
Itโs a big week for the bridge structure. The contractor is scheduled to pour the 3rd vertical section of the South bridge columns this Friday. On the north side, the Bridge Pile cap is currently curing, and crews have begun erecting the rebar for the columns.
๐๐ฅ๐๐ฏ๐๐ญ๐จ๐ซ ๐๐จ๐ฐ๐๐ซ๐ฌ
Procurement and submittals are ongoing. The North Elevator Tower Pile Cap is curing, and we expect to start vertical wall concrete construction by the middle of next week. Work also continues on the internal slabs and components of the South Elevator Tower.
๐๐ซ๐๐๐๐ข๐ ๐๐ฉ๐๐๐ญ๐๐ฌ
โข ALT 1 was opened to normal traffic operations on Sunday, March 1st.
โข Access for work north of the ICW remains open to local traffic only during the ALT 2 construction phase.
๐๐ฐ๐จ-๐๐๐๐ค ๐๐จ๐จ๐ค ๐๐ก๐๐๐
โข Roadway: Construction of ALT 2 entrances, curbs, and sidewalks will continue through the end of March.
โข Bridge & Towers: Work continues on the South Elevator Tower and South Bridge columns.
โข Coming Soon: Construction of the North Bridge Columns and North Elevator Tower Walls is scheduled to begin in mid-March.
The anticipated completion date remains January 8, 2027.